Text of the provision

Art. 1722. If the work cannot be completed on account of a defect in the material furnished by the employer, or because of orders from the employer, without any fault on the part of the contractor, the latter has a right to an equitable part of the compensation proportionally to the work done, and reimbursement for proper expenses made.

(n)

Civil Code of the Philippines, Republic Act No. 386, approved June 18, 1949, effective August 30, 1950. Reproduced in full; verified verbatim against the LawPhil and ChanRobles official-text renderings.

What this article means

If the work cannot be completed due to a defect in the employer's material or the employer's orders, without the contractor's fault, the contractor gets an equitable part of the compensation for work done, plus proper expenses.

Related provisions

Cases citing this article

Compiled automatically from Supreme Court decisions published on LawPhil that expressly cite this article, most frequently cited first. A listing means the decision cites the provision — it is not a statement that the case is the leading authority, and it does not show whether a ruling has since been modified or abandoned. Always read the decision itself.

Note. The text of the provision above is reproduced in full from the official enactment (Republic Act No. 386), verified against the LawPhil and ChanRobles renderings. The annotation and commentary around it are the work of Vivas & Nobles Law Office and are general legal information, not legal advice. How a provision applies to a particular situation depends on facts that only a lawyer reviewing your case can assess.